Mr Chen's SAT GitHub Projects
A walk-through of Mr Chen's own SAT GitHub Projects board — the same kind of project plan you are building for C1-2 and C1-3, demonstrated on a real, complete example.
Watch (≈ video)
What to notice
- PSM stages as lanes. Tasks are grouped into Analysis, Design, Development, Evaluation via the Status field — same structure your board should have.
- Start and end dates on every task. Roadmap View only renders bars for tasks that have both dates set. Empty tasks disappear from the timeline.
- Milestones. Watch how milestones are distinguished from regular tasks — without a label they look identical on the bar.
- Where the gap appears. Even on this complete board, the dependency arrows, critical path highlight, and slack times are not drawn — they have to be added on top of an exported screenshot. See Roadmap View vs Gantt Chart for how to close that gap.